According to the typical factors for estimating project fixed capital cost for a fluids processing plant, what is the factor for piping (fp)?

Correct answer: 0.8

Explanation

This question requires the user to retrieve a specific value from Table 7.5, testing their knowledge of the detailed factorial method for cost estimation and how different cost components are weighted.

Other questions

Question 1

Which category of costs includes the cost of procuring and installing all the process equipment that makes up a new plant, such as vessels, reactors, and columns?

Question 2

According to the AACE International classification, what is the typical accuracy of a 'Class 5' or 'order of magnitude' estimate?

Question 3

A plant with an ISBL capital cost of 50 million USD and capacity of 100,000 tons/year is to be scaled up. What is the estimated ISBL capital cost for a new plant with a capacity of 200,000 tons/year, using the six-tenths rule?

Question 4

What is the primary purpose of a 'Class 3' or 'definitive' estimate?

Question 5

What does the Lang factor relate in capital cost estimation?

Question 6

For a fluids processing plant, what was the original Lang factor proposed in the 1940s?

Question 7

Using the correlation Ce = 17,000 + 1130 * S^1.05 from Table 7.2, what is the estimated purchased cost of a propeller agitator with a driver power (S) of 20 kW?

Question 8

What is the purpose of a cost index like the CEPCI (Chemical Engineering Plant Cost Index)?

Question 9

The purchased cost of a piece of equipment was USD 50,000 when the CEPCI was 402. What is its estimated cost when the CEPCI is 596?

Question 10

Which component of the fixed capital investment includes costs for items like boilers, cooling towers, and waste water treatment plants?

Question 12

What is the materials cost factor (fm) for 316 stainless steel relative to plain carbon steel, according to Table 7.6?

Question 13

A project requires a single piece of equipment with a purchased cost of USD 100,000 on a carbon steel basis. The plant is a fluids processing plant. What is the estimated ISBL installed capital cost if the equipment is made of carbon steel, using the detailed factors from Table 7.5?

Question 14

According to the cost correlation table, what are the units for the size parameter 'S' for a direct contact rotary dryer?

Question 15

What type of cost estimate is based on a completed design and concluded negotiations on procurement of specialized items, and has an accuracy of plus/minus 5 percent to 10 percent?

Question 16

The location factor for building a plant in Germany relative to the USGC was 1.11 in 2003 when the exchange rate was 1 EUR = 1.15 USD. What is the updated location factor in a year when the exchange rate is 1 EUR = 1.30 USD?

Question 17

For a typical petrochemical project, offsite costs are usually estimated to be within what range of ISBL cost if no site details are known?

Question 18

Using the correlation Ce = 80,000 + 109,000 * S^0.8 for a cylindrical furnace, what is the estimated cost for a furnace with a duty (S) of 50 MW?

Question 19

Which of the following is NOT typically considered a direct field cost for an ISBL plant?

Question 20

What is the primary characteristic of working capital in the context of a project's finances?

Question 21

According to the step count method by Bridgewater, a functional unit includes all equipment for a significant process step. Which of the following are generally NOT considered functional units unless they have substantial cost?

Question 22

What is the estimated cost of a single-stage centrifugal pump with a flow rate of 100 liters/s, using the correlation Ce = 8000 + 240 * S^0.9 from Table 7.2?

Question 23

What is a major limitation of using cost correlations from academic textbooks for real-world projects?

Question 24

According to Hand's method, what is the proposed installation factor for a pressure vessel?

Question 25

What is the typical range for a contingency charge on a project where the technology is uncertain?

Question 26

What is the estimated purchased cost of 100 cubic meters of 304 ss pall rings, given the cost for this packing is 8500 USD per cubic meter?

Question 27

How does the text suggest an estimator should handle the cost estimation for a unique reactor design for which no direct cost data is available?

Question 28

What is the typical rule of thumb for engineering costs as a percentage of ISBL plus OSBL costs for smaller projects?

Question 29

What is the estimated cost of a vertical, carbon steel pressure vessel with a shell mass of 100,000 kg, based on the correlation Ce = 11,600 + 34 * S^0.85?

Question 30

When using the factorial method for a plant with alloy construction, if the purchased equipment cost has been obtained on an alloy basis, how should the other installation factors be adjusted?

Question 31

What is the estimated cost of a floating roof tank with a capacity of 5,000 cubic meters, using the correlation Ce = 113,000 + 3250 * S^0.65?

Question 32

What is the primary reason that larger plants tend to have a lower capital cost per unit of production?

Question 33

According to the guidelines in Table 7.8, what is the estimated OSBL cost as a percentage of ISBL cost for a new high solids-handling plant on a new site?

Question 34

The purchased cost for a carbon steel floating head shell and tube exchanger is USD 100,000. If it were built from Monel instead, what would be the estimated ISBL installed cost for this single item in a fluids processing plant, using the detailed factorial and materials factor methods?

Question 35

What is the estimated cost of 50 sieve trays for a column with a diameter of 4.0 meters, using the correlation Cost per tray = 130 + 440 * D^1.8?

Question 36

When mapping simulation data into a cost estimating program like ACCE, what is the default mapping for a plug-flow reactor model (PLUG)?

Question 37

What is the recommended design allowance added to equipment cost by ACCE for a new, unproven process?

Question 38

When costing pressure vessels, why might cost estimating software significantly underestimate the vessel cost for vessels operating at pressures below 5 bara?

Question 39

What is the cost of a plate and frame filter with a capacity of 1.0 cubic meter, using the correlation Ce = 128,000 + 89,000 * S^0.5?

Question 40

A cost estimate of USD 100 million for an ISBL plant is made. Using the factors from Table 7.5 for a fluids-solids plant, what would be the estimated Total Fixed Capital Cost (CFC)?

Question 41

The turnover ratio method for order-of-magnitude estimates relates fixed capital investment to what parameter?

Question 42

What is the lower validity limit (S lower) for the cost correlation of a centrifugal compressor?

Question 43

A cost of USD 1 million was estimated for a project in a location with a location factor of 1.0. What would be the estimated cost for the same project in a location with a factor of 1.60 (e.g., Fort McMurray)?

Question 44

In the context of the factorial method, what is the 'materials factor' (fm) used for?

Question 45

For which piece of equipment is the cost correlation given as Ce = -73,000 + 93,000 * S^0.3 in Table 7.2?

Question 46

According to the text, what is the best source of purchased equipment cost data?

Question 47

What does a cost rating factor, as defined by Moore, take into account when comparing material costs?

Question 48

For the process of biodiesel (FAME) from vegetable oil, what is the upper capacity limit (S_upper) for its cost correlation in Table 7.1?

Question 49

Which of these cost estimation software tools is described as using the ICARUS cost estimation algorithms?

Question 50

What is the estimated cost of an agitated falling film evaporator with an area of 10 square meters, using the correlation Ce = 88,000 + 65,500 * S^0.75?