What is the typical cooling range, the temperature difference between supply and return water, for most cooling towers?

Correct answer: 2.8 to 11.1 C

Explanation

The cooling range of a cooling tower is a key design parameter that represents the temperature drop of the water as it passes through the tower. It reflects a trade-off between the size of the tower and the pumping costs for the circulating water, with most designs operating in the 2.8 to 11.1 C range.

Other questions

Question 1

What is the typical thermal efficiency range of a gas-turbine cogeneration plant with a heat recovery steam generator, as used to generate electricity on site?

Question 2

What is a primary disadvantage of using electric power for heating in large-scale chemical plants compared to using fuels?

Question 3

Fired heaters are typically used for process heating duties above what temperature, which is the approximate limit for high-pressure steam?

Question 4

Estimate the annual cost of providing heat from a fired heater with a process duty of 4 MW. Assume the heater uses both radiant and convective sections, the price of natural gas is 3.20 dollars per MMBtu, and the plant operates for 8000 hours per year.

Question 5

Which of the following is NOT listed as an advantage of using steam as a hot utility in chemical plants?

Question 6

In a typical site steam system, what is the approximate pressure and corresponding condensing temperature for high-pressure (HP) steam?

Question 7

When is a hot oil or specialized heat transfer fluid system most commonly used instead of multiple fired heaters?

Question 8

What is the purpose of the 'blowdown' stream in a cooling water system?

Question 9

What does the Coefficient of Performance (COP) of a refrigeration system represent?

Question 10

A refrigeration cycle is needed to provide 1.2 MW of cooling duty at -5 C. The cycle rejects heat to cooling water at 40 C and has an efficiency of 80 percent of the Carnot cycle efficiency. The plant operates for 8000 hours per year, and electricity costs 0.06 dollars per kWh. What is the estimated annual operating cost?

Question 11

What is a common problem to watch out for when setting up process simulation models, which represents a loss of heat or cooling potential?

Question 12

What is the primary objective of a heat pump when used in the process industries?

Question 13

In the mechanical vapor compression heat pump applied to a distillation column shown in Figure 3.12(b), what is used as the working fluid?

Question 14

The calorific value of a waste gas is to be estimated. The combustion of Dichloroethane (DCE) is given by the reaction C2H4Cl2(g) + 2.5 O2(g) -> 2CO2(g) + H2O(g) + 2HCl(g). The standard heats of formation are: CO2 = -393.8 kJ/mol, H2O = -242.0 kJ/mol, HCl = -92.4 kJ/mol, and DCE = -130.0 kJ/mol. What is the heat of combustion for DCE?

Question 15

What is the term for the set of techniques, developed by Bodo Linnhoff and collaborators, used for designing heat exchanger networks based on a thermodynamic break called a 'pinch'?

Question 16

In a temperature-enthalpy (T-H) diagram for a two-stream heat exchanger problem, what is represented by the overlap of the hot and cold stream curves?

Question 17

What is the thermodynamic significance of the pinch point in a heat exchanger network?

Question 18

What is the primary consequence of designing a heat exchanger network that transfers heat across the pinch?

Question 19

In the problem table method for pinch analysis, how are the interval temperatures (Tint) calculated from the actual stream temperatures (Tact) for a hot stream, given a minimum temperature difference (DTmin)?

Question 20

In the heat cascade calculation of the problem table method, what does the final value at the bottom of the cascade represent after the minimum hot utility has been added at the top?

Question 21

What is the key rule for matching heat exchanger streams immediately ABOVE the pinch to ensure maximum energy recovery?

Question 22

What is the key rule for matching heat exchanger streams immediately BELOW the pinch to ensure maximum energy recovery?

Question 23

When is stream splitting required in the design of a heat exchanger network at the pinch?

Question 24

For simple networks, what is the minimum number of exchangers (Zmin), including heaters and coolers, according to Holmann's rule, where N' is the number of process and utility streams?

Question 25

What defines a 'threshold problem' in pinch analysis?

Question 26

If a process requires heating to a very high temperature necessitating a fired heater, what should be considered for the convective section of the heater to improve energy efficiency?

Question 27

What is the primary challenge for energy management in batch and cyclic processes that is not present in steady-state processes?

Question 28

In the batch preparation of an aqueous solution, 4545 kg of water is heated from 15 C to 80 C in a jacketed vessel. The jacket area is 27.9 m^2, the overall heat transfer coefficient is 285 W m^-2 K^-1, and the steam saturation temperature is 130 C. The specific heat capacity of water is 4.18 kJ kg^-1 K^-1. Estimate the heating time.

Question 29

Which method of heat integration in batch processing is described as being the most thermally efficient, where streams are exchanged as they are pumped from one vessel to the next?

Question 30

What is the typical efficiency of a fired process heater if both the radiant and convective sections are used for process heating?

Question 31

In a process with multiple hot and cold streams, what is the practical minimum temperature difference (DTmin) in a heat exchanger usually between?

Question 32

What does a temperature cross in a heat exchanger simulation indicate?

Question 33

When recovering energy from high-pressure gas streams, what is often done to increase the power generated during expansion if the gas contains condensable components?

Question 34

For a heat integration problem involving a hot stream cooled from 180 C to 60 C and a cold stream heated from 20 C to 135 C, with a DTmin of 10 C, what are the pinch temperatures for the hot and cold streams respectively?

Question 35

Based on the problem described in Section 3.5, with two hot streams and two cold streams and a DTmin of 10 C, what are the minimum hot and cold utility requirements?

Question 36

What is the primary function of demineralized water in a process plant?

Question 37

What is the typical mains pressure at which compressed air is normally distributed in a plant for utility and instrument use?

Question 38

In the context of energy recovery, why is it advisable to avoid mixing streams at different pressures?

Question 39

What type of heat exchangers are commonly used in cryogenic processes to achieve true counter-current performance and very low-temperature approaches?

Question 40

When is it economically justifiable to use process waste products as low-grade fuels?

Question 41

What is the slope of a stream's line on a temperature-enthalpy (T-H) plot proportional to?

Question 42

What is the defining feature of the heat exchange network design for maximum energy recovery, according to the summary rules?

Question 43

In the general expression for the minimum number of exchangers for complex networks, Zmin = N' + L' - S, what does 'S' represent?

Question 44

A simple heat-exchange system is being revamped for 50 percent higher capacity. In the base case, the cold side heat transfer coefficient for the steam heater E102 is 500 W/m^2K. Assuming the coefficient is proportional to the flow rate to the power of 0.8, what is the new cold-side coefficient in the revamp case?

Question 46

What is the primary heat transfer mechanism in a cooling tower that allows water to be chilled?

Question 47

For an ideal refrigeration cycle (a reverse Carnot cycle), how is the Coefficient of Performance (COP) calculated from the evaporator absolute temperature (Te) and condenser absolute temperature (Tc)?

Question 48

In a steam system, what is the purpose of a back-pressure turbine?

Question 49

A process has two hot streams (1 and 2) and two cold streams (3 and 4). Above the pinch, hot stream 1 (CP=3.0) and hot stream 2 (CP=1.0) are available. Cold stream 3 (CP=2.0) and cold stream 4 (CP=4.5) need heating. According to the CPh <= CPc rule, which match is NOT feasible immediately adjacent to the pinch?

Question 50

Which utility fluid is commonly used as 'live steam' for applications like stripping vapor or sterilizing equipment?