What is the key assumption made by the Critical Path Method (CPM) regarding activity times, which distinguishes it from PERT?

Correct answer: That activity times are known with certainty.

Explanation

The fundamental difference between CPM and PERT lies in their handling of time. CPM is a deterministic model, assuming that the duration for each activity is a known and fixed value. PERT, in contrast, is a probabilistic model that accounts for uncertainty.

Other questions

Question 1

The management of projects typically involves three distinct phases. Which of the following correctly lists these three phases as described in the chapter?

Question 2

What is the primary purpose of a Work Breakdown Structure (WBS) in project management?

Question 3

Which project scheduling tool is described as a low-cost means of planning and documenting activities, recording time estimates, and showing overall project time on a timeline with horizontal bars?

Question 4

What is the major difference between PERT and CPM project management techniques?

Question 5

In a project network diagram using the Activity-on-Node (AON) convention, what do the nodes and arrows represent?

Question 6

What is the computed longest time path through a project network called?

Question 7

For an activity in a PERT network, the optimistic time (a) is 1 week, the most likely time (m) is 2 weeks, and the pessimistic time (b) is 9 weeks. What is the expected time (t) for this activity?

Question 8

Using the same activity data where optimistic time (a) is 1 week, most likely time (m) is 2 weeks, and pessimistic time (b) is 9 weeks, what is the variance of this activity's completion time?

Question 9

How is the total project variance calculated in a PERT analysis?

Question 10

What does a zero slack time for an activity signify?

Question 11

An activity in a project has an Earliest Start (ES) of 8, an Earliest Finish (EF) of 13, a Latest Start (LS) of 8, and a Latest Finish (LF) of 13. What is the slack time for this activity?

Question 12

What is the process of shortening the duration of a project in the cheapest manner possible called?

Question 13

An activity has a normal time of 3 weeks at a normal cost of 30,000 dollars, and a crash time of 1 week at a crash cost of 34,000 dollars. What is the crash cost per week for this activity?

Question 14

Which activities should be considered first when crashing a project with a single critical path?

Question 15

What is the purpose of a dummy activity in an Activity-on-Arrow (AOA) network diagram?

Question 16

A project is expected to be completed in 15 weeks with a project standard deviation of 1.76 weeks. What is the probability that the project will be finished in 16 weeks or less?

Question 17

What is the term for a project management style suitable for ill-defined projects, like software development, that relies on collaboration and constant feedback to adjust to unknowns?

Question 18

What is the Earliest Start Time Rule for an activity with multiple immediate predecessors?

Question 19

What is the Latest Finish Time Rule for an activity that is an immediate predecessor to more than one activity?

Question 20

Which of the following is NOT listed as a purpose of project scheduling?

Question 21

According to the text, in what situation might a project organization be most helpful?

Question 22

What are the three time estimates employed in a PERT analysis?

Question 23

Which of the following ethical issues is NOT mentioned as something project managers often deal with?

Question 24

A project manager wants to find a deadline that gives her a 99 percent chance of completion. The project's expected completion time is 15 weeks with a standard deviation of 1.76 weeks. The corresponding Z-value for 99 percent is 2.33. What is the new due date?

Question 25

In a critical path analysis, what is the two-pass process used to determine?

Question 26

An activity in a project has an Earliest Start (ES) of 0, a duration of 3 weeks, and a Latest Start (LS) of 1. What is the slack time for this activity?

Question 27

When crashing a project with multiple critical paths, what is the correct approach according to the text?

Question 28

Which of the following is listed as an advantage of PERT and CPM?

Question 29

Which of the following is identified as a limitation of PERT and CPM?

Question 30

A project consists of five critical activities with variances of 0.11, 0.11, 1.00, 1.78, and 0.11. What is the project variance?

Question 31

In the context of the PERT three-time estimate model, which time estimate is described as the time an activity will take if everything goes as planned?

Question 32

An activity in a network diagram has an ES of 2 and an EF of 4. What is the duration of this activity?

Question 33

When is it possible for a noncritical path to delay a project, according to the text's discussion on variability?

Question 34

An activity has a normal time of 2 weeks and can be crashed to 1 week. The normal cost is 22,000 dollars and the crash cost is 22,750 dollars. What is the crash cost per week?

Question 35

What does a project manager's responsibility for ensuring 'all necessary activities are finished in proper sequence and on time' and 'the project comes in within budget' imply about their role?

Question 36

What type of slack is shared between two or more successive noncritical activities on a path?

Question 37

For a particular project, the expected completion time is 62 weeks and the project variance is 81. What is the project's standard deviation?

Question 38

The critical path for a project is Start-A-C-E-G-H. The activity times are A=2, C=2, E=4, G=5, H=2. What is the total project completion time?

Question 39

In a project organization, team members are temporarily assigned to a project and report to whom?

Question 40

An activity on the critical path has a normal time of 5 weeks and a crash cost per week of 1,500 dollars. It can be crashed by a maximum of 3 weeks. If this activity is crashed by 2 weeks, what is the additional cost?

Question 41

What does the text identify as a major reason for cost overruns and unnecessary delays in projects?

Question 42

A project has an expected completion date of 15 weeks and a project standard deviation of 1.76 weeks. The company needs to finish in 13 weeks. What is the Z-value for this target date?

Question 43

In a WBS, what is the term for the detailed tasks at the lowest level of the hierarchy?

Question 44

Why must a project manager be cautious even if the total project completion time probability is high?

Question 45

An activity has a Latest Start (LS) of 10 and a duration of 3 weeks. What is its Latest Finish (LF)?

Question 46

A project is crashed by one week by reducing the duration of activity A at a cost of 750 dollars. This action causes a second path, Start-B-D-G-H, to become critical. To crash the project by a second week, which option is the most cost-effective if Activity C costs 1,000 dollars, Activity D costs 1,000 dollars, and Activity G (common to both paths) costs 1,500 dollars?

Question 48

An activity in an AOA network starts at event 2 and ends at event 3. Its immediate predecessor is activity X, which starts at event 1 and ends at event 2. What is the relationship between X and this activity?

Question 49

A project's critical path has a total duration of 13 weeks. What does this imply for the project completion?

Question 50

According to the PERT assumptions, what type of probability distribution do total project completion times follow?